Details of planned full or partial Bridge closures for both the M48 Severn Bridge or M4 Prince of Wales Bridge can be found below:

PLEASE NOTE: The bridge status below does not cover the decommissioning works, more information around closures related to the decommissioning of the tolls can be found here.

Provision for wide loads will be maintained unless specifically mentioned above.  Please contact us if you require confirmation.

M4 Prince of Wales Bridge

Date fromDate toDirectionLanesClosure reasonWide loads
14 December 2018 20:00 15 December 2018 06:00 West FULL WESTBOUND CARRIAGEWAY CLOSURE Maintenance No
15 December 2018 20:00 16 December 2018 06:00 West FULL WESTBOUND CARRIAGEWAY CLOSURE Maintenance No
16 December 2018 19:00 17 December 2018 07:00 West FULL WESTBOUND CARRIAGEWAY CLOSURE Maintenance No


M48 Severn Bridge

Date fromDate toDirectionLanesClosure reasonWide loads
17 December 2018 07:00 19 December 2018 07:00 West FULL WESTBOUND CARRIAGEWAY CLOSURE Maintenance No